PROJECT HISTORY

The Hillsdale Drive Extension project is a high priority of the City of Charlottesville and Albemarle County because it is seen as an important link to commercial areas and an alternative to the congested Route 29 Corridor for local, multi-modal traffic. Read more »

A Location Study for this corridor was administered by the City of Charlottesville and guided throughout the process by a Steering Committee that included City of Charlottesville and Albemarle County elected officials and staff, members of local businesses and surrounding community members. Four alternatives were considered as part of the study. In addition to the conceptual design features that were developed, traffic counts, noise readings and other information such as wetland delineation, endangered species, cultural resources and hazardous material investigations were conducted as part of the environmental document (in the form of an environmental assessment was finalized on February 8, 2006.)

The City selected the engineering firm of McCormick Taylor, Inc. to continue the work of the Location Study through the Preliminary Engineering phase by working on the design, environmental, communications, right-of-way and construction management tasks for this project. The design effort was being led by the ten conditions developed by the Steering Committee and supported by the City.

In 2008, VDOT and FHWA approved the NEPA Document re-evaluation. The Design Public Hearing was held on November 16, 2010 at the Senior Center for the extension of Hillsdale Drive from Greenbrier Drive in Albemarle County to Hydraulic Road in the City of Charlottesville. At that time, the roadway extension provided for one lane of traffic in each direction, with dedicated left turn lanes or raised median strips in the center depending on location. The improvements included a 5’ sidewalk on the west side and an 8’ – 10’ shared use path on the east side to accommodate pedestrians and bicycles. On-street parking is provided in limited areas. There were new traffic signals shown at the redesigned intersections with Greenbrier Drive and Seminole Court and a roundabout at the Zan Road crossing. Additional amenities included pedestrian lighting, landscaping features and a potential pocket park.

In 2011 a Bike Lane Study was prepared for this corridor in response to comments received at the Design Public Hearing. Additional bike accomodations were added to the roadway through the use of sharrows and additional signage. The shared use path north of Greenbrier Drive was also converted to on-road bike lanes to provide better a transition. After a thorough review of the comments received at the hearing, the City of Charlottesville approved the major design features on February 22, 2011 and the County of Albemarle Board of Supervisors concurred on March 2, 2011.

Both the City and County are committed to working with the community to advance this project while providing accommodations to the local residents, commuters and businesses involved.

ENVIRONMENTAL ACTIVITIES

The project team is working closely with the City of Charlottesville to conduct a reevaluation of the NEPA document prepared for the Hillsdale Drive Extension project. The original Environmental Assessment (EA) was signed on in September 2004 and a Finding of No Significant Impact (FONSI) was approved by the Federal Highway Administration (FHWA) in March 2006. Due to slight design changes, a reevaluation of the EA/FONSI was completed by the City and approved by VDOT and FHWA in the spring of 2008.

A new reevaluation of the environmental documentation is underway to ensure the project is meeting current regulations and best design practices. This work is expected to be completed in spring 2015.

RIGHT OF WAY ACQUISITION

Throughout the design process it was our goal to develop solutions that address both the roadway project and the various needs of the users of this new connection. The project team will continue to work with the property owners through right of way negotiations and the stakeholders through a Stakeholders Committee to provide a facility that will:

  • Safely accommodate the projected traffic volumes
  • Minimize overall property impacts
  • Minimize the loss of parking spaces
  • Safely provide for needed access
  • Accommodate the necessary drainage needs in a confined area
  • Provide the best design solutions to satisfy property owners and tenants of the existing homes and businesses

Relevant Documents

Hillsdale Drive Location Study Report

The Hillsdale Drive Location Study was undertaken to determine the best location for an extension of Hillsdale Drive. The study followed the process established by the National Environmental Policy Act (NEPA) and the Virginia Department of Transportation (VDOT).

Review the complete Location Study Report »

Review the Resolution of the Commonwealth Transportation Board »

The Impact of Hillsdale Drive Extension on Local Businesses and Economy

The Firm of Chmura Economics and Analytics was hired by the City of Charlottesville to estimate the economic impact of the Hillsdale Drive Extension. This Report was developed as part of the Location Study.

Review the complete report »

Hillsdale Drive Extension Environmental Assessment

A Draft Environmental Assessment was developed for the Location Study. This Document evaluated environmental impacts for all of the alternative alignments which were under consideration during the Location Study.

Review the full Environmental Assessment (6 MB) »

Value Engineering


Value Engineering (VE) is a systematic, creative study process conducted by engineers and technicians to obtain optimum value for every dollar spent. Learn more about the VE Study for this project here.